LEAK REPAIR OF 900MM DIAMETER TRANSMISSION LINE IN BARANGAY TAGUIBO, BUTUAN CITY (02/15/2024 as of 8:35AM)

WATER SUPPLY INTERRUPTION
WATER STATUS UPDATE

LEAK REPAIR OF 900MM DIAMETER TRANSMISSION LINE IN BARANGAY TAGUIBO, BUTUAN CITY
(02/15/2024; as of 8:35AM)

The Butuan City Water District (BCWD) has started with the leak repair of the 900mm diameter transmission line near Taguibo Elementary School, Brgy. Taguibo, Butuan City at around 5:30A.M. of February 15, 2024.

Water pressure monitoring was conducted and it was seen that there is already zero (0) water pressure in the entire water system of BCWD as of press time. As such, as the entire service area of BCWD has no water.

BCWD is sharing with you pictures of the current leak repair being conducted as an update (see attached photos).

Please bear with us.